18 km of the finishing layer of the coating was laid on the Kharkiv ring road

13 July 2021, 17:58 | Economy
photo glavnoe.ua
Text Size:

On the Kharkiv ring road, 18 km of the finishing layer of crushed stone-mastic asphalt concrete was laid. Within the framework of the Big Construction Program of President Vladimir Zelensky, 50.7 km of the old coating layer was milled.

As reported in the Service of Highways in the Kharkiv region, 49.2 km of road surface have already been asphalted in a leveling layer of fine-grained asphalt concrete mixture.

“Powerful special equipment works almost around the clock, everything in order to provide safe and comfortable travel as soon as possible,” the SAD noted..

Now work is underway in such areas:.

M-03 \;

М-03-03 "

In addition, to link the road surface between the layers of asphalt concrete, the road workers are laying composite reinforcement, 28.1 thousand. sq..

“At the work sites, the traffic is organized along one half of the carriageway in reverse mode.

We apologize for the inconvenience and ask you to treat this situation with understanding, "

Now on the section of the road M-03 "

In particular, on the section of the road M-03-03 "

Also, in parallel, work is being carried out on additional transition-speed lanes, removal of shrub growth from the shoulders and installation of boards, dismantling of the barrier fence, dismantling the old and installing a new side stone.

The first section: highway M-03 "

Second section: M-03 "

Third section: M-03-03 "

Kharkiv ring road consists of sections of 5 roads with a total length of 82 km. In total, within the framework of the Program of President Vladimir Zelensky " The project cost is UAH 1.8 billion, the implementation period is 2 years.