Large-scale reconstruction of the boiler house of the KP " Shakespeare, 17 in Shevchenko district.
Today, on August 9, the secretary of the Kharkiv City Council Igor Terekhov got acquainted with the progress of the reconstruction of the object, according to the press service of the City Council.
As reported in KP " Over the past few decades, the boiler room equipment has not been overhauled and last winter it gave a serious breakdown: cases of defects both on boilers and on auxiliary equipment became more frequent.. Therefore, after the end of the heating season, they began a large-scale reconstruction..
The company noted that there are five boilers in the boiler room, four of which were subject to major repairs.. So, for today, three hot water boilers have already been completely repaired, one is in operation. In addition, two modern pumps were installed in the boiler house, which consume 30% less electricity, which means that in the new heating season, the company will be able to save up to UAH 10-12 million on one such pump..
As Igor Terekhov noted, the boiler room was also equipped with a system that will ensure uninterrupted operation in the event of a power outage..
“It is very important for us to prepare boiler houses so that in the heating season Kharkiv citizens receive heat and hot water without interruption.. We overhaul old boilers, relocate heating networks, install modern equipment. All this will allow us to maintain a balance and not raise tariffs for the population, "