Large-scale reconstruction of the boiler house of the KP " Dispatch, 27-a in Osnovyansky district.
As reported in KP " As a result, the boiler house mainly supplied only heat, since it could not provide residents with hot water all year round after the end of the heating season.. Therefore, KP "
So, to date, six German-made boilers equipped with modern automation have already been installed in the boiler room.. Four of them are designed for heating the coolant, the rest are for hot water supply. In addition, all pumping equipment and shut-off valves were replaced at the boiler house, new chimneys, high-quality plate heat exchangers, a compact automatic water softening system and new hot water storage tanks were installed..
“We will launch the boiler house in the new heating season.
With the start of its operation, residents of the district will be able to receive high-quality hot water in winter and summer, and will also be provided with uninterrupted heat supply.. In addition, the installation of new boilers will give the company a 10% gas saving "
The reconstruction of the boiler house is being carried out within the framework of the project " In accordance with the contract concluded with the French company ENERTEX, a total of 10 boiler houses will be built and refurbished in the city, six of which will start operating in the heating season 2021-2022..