The project of reconstruction of the Gostiny Dvor: what the developer promises

14 June 2017, 12:14 | The Company
photo УРА-Информ
Text Size:

This was reported by the director of PrJSC "Ukrrestavratsi" Klochko I. The works are ready to proceed immediately after obtaining permission to perform construction work - to give the building promise in the shortest time and create a real "Pearl of Podol" for residents and visitors of the city.

In 2014, a permit to perform construction work was quashed at the request of a group of "pseudo advocates", which led to the suspension of construction work. PJSC "Ukrrestavratsiya" at this stage spent about 120 million hryvnia, and to complete the construction work, according to preliminary estimates, it is necessary about 300 million hryvnia. PJSC "Ukrrestavratsiya" repeatedly applied to the State Architectural and Stoat Inspectorate of Ukraine to obtain a permit, but in return receives only unsubscribes. The lack of such a permit makes it impossible to carry out construction work, including the roofing, which was purchased by the private company "Ukrrestavratsiya" as early as 2014, "said Director Klochko I.

Director Klochko I. Noted that "Ukrrestavratsiya" is open for dialogue with the city public on the discussion of the functional purpose of the premises in the Gostiny Dvor building. The enterprise is sure: the claims from the activists and the blocking of construction work for the reconstruction of the Gostiny Dvor building are aimed at their samopiar for political dividends, as well as the deliberate discrediting and creation of the negative image of PJSC "Ukrrestavratsia", with the aim of pressure for further owners change. "So, first," pseudo advocates "block construction work, revoke the permission to conduct them, and then apply to the court for the purpose of early termination of the lease of the building, arguing that due to the stoppage of construction work - the building Is destroyed, - the press service noted..

Recall, the primary function of the Gostiny Dvor was always trade. As early as 1808, the Kyiv City Commission for Income and Expenditure Management granted the Kiev Governor the right to withdraw bargaining space on the Kontraktova Square, and in 1813 the governor received an order for the appointment of trade rows and the distribution of shops, totaling 96 units.

In the 1970s, the Gostiny Dvor building was in critical architectural and technical condition, and in 1983, after carrying out engineering and geological studies of soils and load-bearing structures, it was decided to demolish the building. Research, design and construction work on the Gostiny Dvor building continued from 1971 to 1990, and in the construction part - from 1983 to 1990.

In 2011, the "State Research Institute of Building Constructions" conducted a survey of the building and recorded a poor technical condition. PJSC "Ukrrestavratsiya" began preparation and collection of documents necessary for repair works of the building, and in 2012 - construction work began, namely "Reconstruction of the building for a shopping center", that is, the reproduction of the primary function of the Gostiny Dvor - trade.

Recall, PJSC "Special Scientific and Restoration Project Construction and Production Enterprise" Ukrrestavratsiya ", has been a tenant of the Gostiny Dvor building since 1994.

"Ukrrestavratsiya" has 70 years of history and experience, includes more than 1500 restored and restored buildings, monuments and monuments, including world famous ones such as Sophia Kievskaya, St. Andrew's Church, St. Cyril's Church, Nativity Church, St. Vladimir's Cathedral, National Theater of Opera And ballet in Kiev, opera houses in Odessa, Lviv and Chernivtsi, Kamenets-Podolsky fortress, Khotyn and Sudak, wooden churches of Drogobych and Transcarpathia and many others: historical buildings of the Bessarabian quarter, house B. Gorodetsky - house with chimeras (state residence), Administration of the President of Ukraine and others.