Reconstruction of the Dnieper HPP-1 will increase the production of energy

15 November 2018, 23:57 | Economy
photo glavnoe.ua
Text Size:

PJSC "Ukrhydroenergo" intends to conduct a large-scale reconstruction of the equipment of the Dnieper HPP-1. The modernization will last 5 years, during which time € 62 million will be invested in the project.

"Work on the rehabilitation of equipment Dneproges-1 will last for 5 years and must finish in 2021. In particular, the updated third hydrounit should start work in June 2020, the second in October 2021.. The launch of the first is scheduled for the end of August 2021. In general, 62 million euros will be invested in the project, "- says Uprom referring to the press service of PJSC" Ukrhydroenergo ".

Large-scale rehabilitation equipment will allow increasing the total generating capacity of the Dnieper hydroelectric power plant by 30 MW. At the same time, it will also be possible to extend the station’s work by at least half a century..



In "Ukrgidroenergo" explain the expediency of complex replacement of equipment by the fact that the hydraulic units produced by the American General Electric Corporation have been working for more than 70 years, having exhausted their resources and warranty obligations for the generation of electricity.

Add that at the end of the summer Austrian experts have already started working on the site for the reconstruction. On August 27, the third hydroelectric unit was decommissioned, which produced almost 18 billion kW. October 26, hydraulic unit No. 2 stopped. Next in line is the first car.

Together with the reconstruction of equipment at the Dneprovskaya HPP-1, work continues on the modernization of the Dneprovskaya HPP-2.