Sverdlovskaya CHP Plant repairs chimney. It has been in operation since 1954 and is designed to divert the combustion products of boilers, one of which heats the water of consumers in the Uralmash microdistrict. The project is implemented to eliminate a number of defects identified during the examination of industrial safety, according to press-service of the ETK.
The work will be completed by the end of June. To implement this project, the company sent 2.8 million rubles.
At the facility, specialists repair metal structures (traffic lights and ladders), the pipe head, reinforced concrete structures inside and outside the trunk, flues, lightning protection equipment, update the marking "color".