In Zaporozhye checked 200 thousand housing estates

03 November 2017, 20:12 | The Company 
фото с УРА-Информ

So, in the process of preparation for the heating season, the gas workers carried out maintenance, as well as overhauling the gas pipelines. The diagnostics and examination of gas supply devices. Such data was disseminated by the press service of the company.

Employees of "Zaporizhzhgaz" recently carried out a technical condition check of approximately seven thousand kilometers of underground as well as above-ground gas pipelines. In the course of the inspection, the inspection was also carried out, the equipment was adjusted, the repair of the structures.

As reported URA-Inform, in the capital of 800 houses are still without heating, because the loads can not withstand the heat network.

Источник: УРА-Информ