For the ChNPP repository, a radiation monitoring system will be created

30 August 2017, 14:31 | Economy 
фото с УРА-Информ

So, will be purchased imported equipment - to 123.52 million hryvnia. The Chornobyl nuclear power plant will soon be equipped with a radiation monitoring system - for 127 million hryvnia. Such data was distributed by "Our money", referring to the information from "Prozorro".

Thus - on June 28, on the results of a competitive dialogue, SSG Chornobyl NPP ordered the construction of a radiation monitoring scheme ISF-1 for Ukrenergomontazh - UAH 127 million. Speech - about one of the two storage facilities for nuclear fuel of a "wet" type - at the ChNPP site.

As reported URA-Inform, in the zone of the Chernobyl nuclear power plant was previously found household rubbish.