The power unit No. 4 of Rivne NPP was connected to the grid

22 August 2017, 12:21 | Economy 
фото с УРА-Информ

This was reported in the press service of "Energoatom".

According to recently received data, repairs were performed in 48 calendar days with the planned 52.

During repairs, routine maintenance, and a variety sverhreglamentnyh work aimed at improving the safety.

As of 8 o'clock on August 22 all four power units of Rivne NPP with a total load of 2660 MW. There are no remarks to the work of the main equipment of operating power units and personnel.

In addition, the radiation, fire-prevention and ecological status of the RNPP and the adjacent territory did not change and is within the limits of effective standards.

Recall, as previously reported, "URA-Inform", the power unit No. 1 of Zaporizhzhya NPP has been disconnected from the grid for carrying out the average scheduled repair.